| 2008 Capital Budget
Revised June 2008
The following is an abbreviated list of the District's revised 2008 Capital Budget, as approved by the Board of Trustees. For more detailed information, feel free to contact us.
Transmission and Distribution Replacement Projects
- Marshall Point Road , Kennebunkport , 1,350' - Deferred until '09
- Fisher's Lane, Cape Porpoise , 600' - Completed
- Brown Street , Kennebunk, 500' - Deferred until '09
- Alewive Road, West Kennebunk, 1,000' - Completed
- Island Avenue, Wells, 200' - Completed
- Devito Lane , Wells, 140' - Completed
- Route One (SRF Project), Wells, 3,100'
- Webhanent Drive , Wells, 800' - Completed
- Orchard Road, Wells, 350'
- Route One, Ogunquit, 1,350' - Completed
- Shipper Joe's Point Road, Kennebumkport, 1300'
Other Transmission and Distribution Projects
- Webhanent Drive , Wells service changeovers and 1,100' abandonment - Completed
- Ocean Avenue , Wells, service changeovers and 3,250' abandonment - Completed
- Miscellaneous oversizing of developer mains
Service Line and Meter Replacements
Hydrants and Valves
Vehicle Fleet (Truck) Replacements
Equipment (Distribution, Plant, Facilities & Business Office)
Tanks and Boosters
Filtration Plant Infrastructure
Groundwater Source Development
Structures and Grounds
Total Approved 2007 Capital Budget
$1,506,150
$85,500
$203,000
$76,800
$81,768
$171,000
$46,000
$110,500
$118,500
$36,500
$2,435,718
|